Montáž wallboxu / Detached house
From selecting the power rating to the inspection report. We first check the circuit breaker and what is running in the house, and only then consider the charging station brand.
The most common question is whether to choose 11 or 22 kW. The answer almost always starts with the main circuit breaker. An 11 kW wallbox draws around 16 A per phase, while a 22 kW unit requires around 32 A. A house with a 3×25 A main breaker, an air-to-air heat pump and an induction hob has no spare capacity for 22 kW, even if the vehicle supports it.
The second part of the answer lies with the vehicle. Some cars have an on-board charger limited to 11 kW, in some cases even to 7,4 kW. In such cases, the 22 kW paid capacity will never be utilised.
The third factor is how long the vehicle remains parked. When left overnight, it will charge even at 11 kW. Faster charging only addresses situations where the battery must be replenished within an hour or two between trips.

If the house has no spare capacity, there are two options. Either upgrade the main fuse, which requires negotiations with the distributor and permanently higher payments based on its size. Or implement dynamic management: the station measures the house's total consumption and automatically reduces charging when an oven is switched on or a pump activates. The vehicle charges slightly slower, but nothing trips out and the payment for the fuse remains unchanged.
For most homes, the second option is cheaper. However, it requires a station capable of this and metering on the main supply, so it must be arranged in advance, not added later.
| 11 kW | 22 kW | Single-phase 3.7 kW | |
|---|---|---|---|
| Consumption | approx. 16 A per phase | approx. 32 A per phase | approx. 16 A on one phase |
| Overnight charging | a fully charged battery of a standard car | The same, just faster. | tens of kilometres of range |
| When it makes sense | the vast majority of households | two trips per day, quick top-up | low traffic volumes, weak connection |
| What to watch out for | The vehicle's onboard charger may be weaker. | circuit breaker and distribution network operator consent | insufficient for daily commuting over 50 km |
The most common reason for delays is not the installation but the distributor. Therefore, we submit the paperwork at the very beginning and schedule the installation only for a confirmed date.
For most households, 11 kW is sufficient. The car stands overnight and even 11 kW will charge it from nearly empty in that time. 22 kW makes sense where the car must be charged quickly between two trips, and not every vehicle can accept this anyway. The main fuse also decides: 22 kW is 32 A per phase, which often becomes a problem in a house with an air-to-air heat pump.
It is possible, just slower. A single-phase installation provides approximately 3.7 kW, which overnight equates to tens of kilometres of range. This suffices for short trips, but for daily commutes exceeding fifty kilometres it often falls short. We verify this from utility bills, not estimates.
The location where you park and where the cable reaches your vehicle's charging port, not where a free wall is available. The port position varies by manufacturer. The second criterion is the distance from the distribution board, as every metre of cabling incurs cost. During the site inspection, these two factors are assessed together.
Sometimes yes. When the reserved power is increased, the main fuse changes and so does the payment for its size. When switching to a tariff favourable for charging, the electricity meter usually changes as well. Both are handled by the distributor and are the most common reason why implementation takes weeks instead of days.
We only need the car model, the location for the charging station, and your main fuse rating. We will contact you within 24 hours on working days to ask further questions and arrange a site visit. The visit and proposal are free of charge and non-binding.
Call on working days and we'll go through it together in ten minutes.
775 654 443